Victorias City Government Center set for September 2027 completion

The current Victorias City Hall is expected to become a museum on the city’s sugar heritage, history, and culture,*

The new Victorias City Government Center is ahead of schedule and set for completion by September 2027, Victorias City Engineer Engr. Mary Jean Majaducon confirmed on Saturday, November 14.

Majaducon said work on the government center is now at 37 percent  based on the timeline, while only about 27 percent of the contracted price has been downloaded to the project contractor, a press release from the office of Rep. Javier Migue Benitez (Neg. Occ., 3rd District) said Friday, Nov. 20.

The three-storey building will have a floor area of about 7,120.50 square meters and will house the executive and legislative branches of the city government, along with key administrative offices. It is located within the 25-hectare Sidlak Victorias Global City development at Hacienda Loreto, Barangay XIII.

The government center is one of three developments under the Sidlak Victorias Global City initiative, together with the Sidlak Land Development Project and the Sidlak Residential Complex.

The Php 550-million government center is funded through the Php 1.086-billion loan the city secured from the Development Bank of the Philippines (DBP) while Rep. Javier Miguel “Javi” L. Benitez was mayor.

The same loan covers road and drainage improvements, the upgrading of the city coliseum, the new motor pool building, and other priority infrastructure projects.

Majaducon said all major projects under the city’s infrastructure program are moving ahead of schedule, with several already completed and in use while the city is yet to meet its full obligations.

The motor pool facility, for instance, was completed in May while the city has paid only 70 percent  of its total cost, he said.

Aside from the motor pool inaugurated on Saturday, the upgraded Victorias City Coliseum has hosted major national events this year, including ABS-CBN’s ASAP XP on June 7, which drew more than 13,000 spectators across two back-to-back shows; the final leg of the Premier Volleyball League (PVL) On Tour on August 22, played before a full-house crowd; and the second LegisHear in Negros Island Region on October 2-3, 2026.

Benitez said the new government center, envisioned as a major landmark of the city, reflects Victorias City’s continuing growth and modernization.

He added that the progress reflects the steady implementation of the infrastructure investments started during his administration.

Once the new center is in operation, the current Victorias City Hall is expected to become a museum on the city’s sugar heritage, history, and culture, in partnership with the National Museum of the Philippines, the press release said.*