DPWH: No definite timetable for Guimaras-Negros bridge 

Work on the detailed engineering design for the Panay-Guimaras and Guimaras-Negros bridges is now  ongoing,  Sanny Boy Oropel, Department of Public Works and Highways 6 acting regional director, said on Monday, April 8. 

The detailed engineering design for the 13-kilometer nmeter Panay-Guimaras bridge  will be completed by December 2024, and   the 19.47 –kilometer  Guimaras-Negros bridge by December 2025, he said. 

The civil works for the Panay-Guimaras bridge  is targeted to start in the second  semester of  2025 and will be completed before the term of President Ferdinand Marcos Jr. ends in 2028 

It is targeted to  be operational by the end of June 2028    

Oropel said he cannot give a definite timetable for the start of the civil works for the Guimaras to Negros bridge.*   